Your Perfect Assignment is Just a Click Away
We Write Custom Academic Papers

100% Original, Plagiarism Free, Customized to your instructions!

glass
pen
clip
papers
heaphones

Construction Management

Construction Management

Construction Management
Answer Discussion Questions 1&2

1. In your opinion, why it is important to identify constraints in the project schedule?

2. How should a schedule be presented to an owner? Please discuss what are the key points to be included?

Respond to student’s discussion answer below

P U

1. A schedule constraint is a limitation added on a project schedule that affects the start or end date of an activity. Schedule constraints can take the form of fixed imposed dates for a work item, it can be used to restrict the start of an activity to occur no earlier than a specified date, rather than allowing the dates to be determined by the planning process. As soon as possible, Start no earlier than, finish no later than are some of the constrain we add in a project schedule. It is important to identity because when a constraint date is applied to a work item, that date takes precedence over dependency resolution dates during the scheduling process.

Respond

2. Many project owners prefer network diagrams when project schedule is presented to them by the contractor. The network diagram is a way to visualize the interrelationships of project activities. Network diagrams provide a graphical view of the tasks and how they relate to one another. The tasks in the network are the work packages of the WBS. All the WBS tasks must be included in the network because they must be accounted for in the schedule. Project schedules are to be provided to monitor the progress of the contractor and subcontractors relative to established schedules and to serve as status reports to the owner. The contractor administrator will discuss how the project stands with respect to the owner’s construction schedule and delivery.

Respond

D B

It is important to identify constraints in a schedule because they add elements, they may be unique to the project. As an example I worked on a high-rise building renovation project that scheduled task to subcontractors by floor completion but nothing could be done on the next floor until the asbestos abatement was complete, thus a start no earlier than constraint is appropriate.

Respond

A good schedule to present to owners would be a bar chart. Bar charts are simple and easy to follow the logic involved. The bar chart should include the duration, late start and finish dates without float. This way if task and the overall project is completed early the manager is looked upon favorably instead of setting an expectation to do so.

Respond

Answer

Discus

sion Que

s

tion

s

1&

2

1.

In your opinion,

why it is important to identify constraint

s

in the project schedule?

2.

How should a schedule be presented to an owner?

Please discuss what are the

key

points to be

included?

R

es

pon

d to

student’s

discussion answer

below

P U

1.

A schedule constraint is a limitation added on a project schedule that affects the start or end

date of an activity. Schedule constraints can take the form of fixed imposed dates for a work

item, it can be

used to restrict the start of an activity to occur no earlier than a specified date,

rather than allowing the dates to be determined by the planning process. As soon as possible,

Start no earlier than, finish no later than are some of the constrain we add

in a project

schedule.

It

is important to identity because when a constraint date is applied to a work item, that date

takes precedence over dependency resolution dates during the scheduling process.

Respond

2.

Many project owners

prefer

network diagrams when project

schedule is presented to them by

the contractor. The network diagram is a way to visualize the interrelationships of project

activities. Network diagrams provide a graphical view of the tasks and how they relate to one

another. The tasks in the network ar

e the work packages of the WBS. All the WBS tasks must be

included in the network because they must be accounted for in the schedule. Project schedules

are to be provided to monitor the progress of the contractor and subcontractors relative to

established

schedules and to serve as status reports to the owner. The contractor administrator

will discuss how the project stands with respect to the owner’s construction schedule and

delivery.

Respond

D

B

It is important to identify constraints in a schedule because they add

elements,

they may be unique

to the project. As an example I worked on a high

rise building renovation project that scheduled tas

k

to subcontractors by floor completion but nothing could be done on the next floor until the asbestos

abatement was complete, thus a start no earlier than constraint is appropriate.

Respond

A good schedule to present to owners would be a bar chart. Bar charts are simple and easy to follow the

logic involved. The bar chart should include the duration, l

ate start and finish dates without float. This

way if task and the overall project is completed early the manager is looked upon favorably instead of

setting an expectation to do so.

Respond

Answer Discussion Questions 1&2

1. In your opinion, why it is important to identify constraints in the project schedule?

2. How should a schedule be presented to an owner? Please discuss what are the key points to be

included?

Respond to student’s discussion answer below

P U

1. A schedule constraint is a limitation added on a project schedule that affects the start or end

date of an activity. Schedule constraints can take the form of fixed imposed dates for a work

item, it can be used to restrict the start of an activity to occur no earlier than a specified date,

rather than allowing the dates to be determined by the planning process. As soon as possible,

Start no earlier than, finish no later than are some of the constrain we add in a project schedule.

It is important to identity because when a constraint date is applied to a work item, that date

takes precedence over dependency resolution dates during the scheduling process.

Respond

2. Many project owners prefer network diagrams when project schedule is presented to them by

the contractor. The network diagram is a way to visualize the interrelationships of project

activities. Network diagrams provide a graphical view of the tasks and how they relate to one

another. The tasks in the network are the work packages of the WBS. All the WBS tasks must be

included in the network because they must be accounted for in the schedule. Project schedules

are to be provided to monitor the progress of the contractor and subcontractors relative to

established schedules and to serve as status reports to the owner. The contractor administrator

will discuss how the project stands with respect to the owner’s construction schedule and

delivery.

Respond

D B

It is important to identify constraints in a schedule because they add elements, they may be unique

to the project. As an example I worked on a high-rise building renovation project that scheduled task

to subcontractors by floor completion but nothing could be done on the next floor until the asbestos

abatement was complete, thus a start no earlier than constraint is appropriate.

Respond

A good schedule to present to owners would be a bar chart. Bar charts are simple and easy to follow the

logic involved. The bar chart should include the duration, late start and finish dates without float. This

way if task and the overall project is completed early the manager is looked upon favorably instead of

setting an expectation to do so.

Respond

Applied Sciences
Architecture and Design
Biology
Business & Finance
Chemistry
Computer Science
Geography
Geology
Education
Engineering
English
Environmental science
Spanish
Government
History
Human Resource Management
Information Systems
Law
Literature
Mathematics
Nursing
Physics
Political Science
Psychology
Reading
Science
Social Science
Home
Homework Answers
Blog
Archive
Tags
Reviews
Contact
google+twitterfacebook
Copyright © 2021 HomeworkMarket.comHOMEWORKMARKET.COM – YOUR HOMEWORK ANSWERSHomeworkMarket
chat0
Home.Literature.
Help.
Log in / Sign up
Construction Management
profile
moore05

AnswerDiscussionQuestionsandResponsesw3.docx
Home>Engineering homework help>Construction Management
Answer Discussion Questions 1&2

1. In your opinion, why it is important to identify constraints in the project schedule?

2. How should a schedule be presented to an owner? Please discuss what are the key points to be included?

Respond to student’s discussion answer below

P U

1. A schedule constraint is a limitation added on a project schedule that affects the start or end date of an activity. Schedule constraints can take the form of fixed imposed dates for a work item, it can be used to restrict the start of an activity to occur no earlier than a specified date, rather than allowing the dates to be determined by the planning process. As soon as possible, Start no earlier than, finish no later than are some of the constrain we add in a project schedule. It is important to identity because when a constraint date is applied to a work item, that date takes precedence over dependency resolution dates during the scheduling process.

Respond

2. Many project owners prefer network diagrams when project schedule is presented to them by the contractor. The network diagram is a way to visualize the interrelationships of project activities. Network diagrams provide a graphical view of the tasks and how they relate to one another. The tasks in the network are the work packages of the WBS. All the WBS tasks must be included in the network because they must be accounted for in the schedule. Project schedules are to be provided to monitor the progress of the contractor and subcontractors relative to established schedules and to serve as status reports to the owner. The contractor administrator will discuss how the project stands with respect to the owner’s construction schedule and delivery.

Respond

D B

It is important to identify constraints in a schedule because they add elements, they may be unique to the project. As an example I worked on a high-rise building renovation project that scheduled task to subcontractors by floor completion but nothing could be done on the next floor until the asbestos abatement was complete, thus a start no earlier than constraint is appropriate.

Respond

A good schedule to present to owners would be a bar chart. Bar charts are simple and easy to follow the logic involved. The bar chart should include the duration, late start and finish dates without float. This way if task and the overall project is completed early the manager is looked upon favorably instead of setting an expectation to do so.

Respond

Answer

Discus

sion Que

s

tion

s

1&

2

1.

In your opinion,

why it is important to identify constraint

s

in the project schedule?

2.

How should a schedule be presented to an owner?

Please discuss what are the

key

points to be

included?

R

es

pon

d to

student’s

discussion answer

below

P U

1.

A schedule constraint is a limitation added on a project schedule that affects the start or end

date of an activity. Schedule constraints can take the form of fixed imposed dates for a work

item, it can be

used to restrict the start of an activity to occur no earlier than a specified date,

rather than allowing the dates to be determined by the planning process. As soon as possible,

Start no earlier than, finish no later than are some of the constrain we add

in a project

schedule.

It

is important to identity because when a constraint date is applied to a work item, that date

takes precedence over dependency resolution dates during the scheduling process.

Respond

2.

Many project owners

prefer

network diagrams when project

schedule is presented to them by

the contractor. The network diagram is a way to visualize the interrelationships of project

activities. Network diagrams provide a graphical view of the tasks and how they relate to one

another. The tasks in the network ar

e the work packages of the WBS. All the WBS tasks must be

included in the network because they must be accounted for in the schedule. Project schedules

are to be provided to monitor the progress of the contractor and subcontractors relative to

established

schedules and to serve as status reports to the owner. The contractor administrator

will discuss how the project stands with respect to the owner’s construction schedule and

delivery.

Respond

D

B

It is important to identify constraints in a schedule because they add

elements,

they may be unique

to the project. As an example I worked on a high

rise building renovation project that scheduled tas

k

to subcontractors by floor completion but nothing could be done on the next floor until the asbestos

abatement was complete, thus a start no earlier than constraint is appropriate.

Respond

A good schedule to present to owners would be a bar chart. Bar charts are simple and easy to follow the

logic involved. The bar chart should include the duration, l

ate start and finish dates without float. This

way if task and the overall project is completed early the manager is looked upon favorably instead of

setting an expectation to do so.

Respond

Answer Discussion Questions 1&2

1. In your opinion, why it is important to identify constraints in the project schedule?

2. How should a schedule be presented to an owner? Please discuss what are the key points to be

included?

Respond to student’s discussion answer below

P U

1. A schedule constraint is a limitation added on a project schedule that affects the start or end

date of an activity. Schedule constraints can take the form of fixed imposed dates for a work

item, it can be used to restrict the start of an activity to occur no earlier than a specified date,

rather than allowing the dates to be determined by the planning process. As soon as possible,

Start no earlier than, finish no later than are some of the constrain we add in a project schedule.

It is important to identity because when a constraint date is applied to a work item, that date

takes precedence over dependency resolution dates during the scheduling process.

Respond

2. Many project owners prefer network diagrams when project schedule is presented to them by

the contractor. The network diagram is a way to visualize the interrelationships of project

activities. Network diagrams provide a graphical view of the tasks and how they relate to one

another. The tasks in the network are the work packages of the WBS. All the WBS tasks must be

included in the network because they must be accounted for in the schedule. Project schedules

are to be provided to monitor the progress of the contractor and subcontractors relative to

established schedules and to serve as status reports to the owner. The contractor administrator

will discuss how the project stands with respect to the owner’s construction schedule and

delivery.

Respond

D B

It is important to identify constraints in a schedule because they add elements, they may be unique

to the project. As an example I worked on a high-rise building renovation project that scheduled task

to subcontractors by floor completion but nothing could be done on the next floor until the asbestos

abatement was complete, thus a start no earlier than constraint is appropriate.

Respond

A good schedule to present to owners would be a bar chart. Bar charts are simple and easy to follow the

logic involved. The bar chart should include the duration, late start and finish dates without float. This

way if task and the overall project is completed early the manager is looked upon favorably instead of

setting an expectation to do so.

Respond

Applied Sciences
Architecture and Design
Biology
Business & Finance
Chemistry
Computer Science
Geography
Geology
Education
Engineering
English
Environmental science
Spanish
Government
History
Human Resource Management
Information Systems
Law
Literature
Mathematics
Nursing
Physics
Political Science
Psychology
Reading
Science
Social Science
Home
Homework Answers
Blog
Archive
Tags
Reviews
Contact
google+twitterfacebook
Copyright © 2021 HomeworkMarket.com

Order Solution Now

Our Service Charter

1. Professional & Expert Writers: Topnotch Essay only hires the best. Our writers are specially selected and recruited, after which they undergo further training to perfect their skills for specialization purposes. Moreover, our writers are holders of masters and Ph.D. degrees. They have impressive academic records, besides being native English speakers.

2. Top Quality Papers: Our customers are always guaranteed of papers that exceed their expectations. All our writers have +5 years of experience. This implies that all papers are written by individuals who are experts in their fields. In addition, the quality team reviews all the papers before sending them to the customers.

3. Plagiarism-Free Papers: All papers provided byTopnotch Essay are written from scratch. Appropriate referencing and citation of key information are followed. Plagiarism checkers are used by the Quality assurance team and our editors just to double-check that there are no instances of plagiarism.

4. Timely Delivery: Time wasted is equivalent to a failed dedication and commitment. Topnotch Essay is known for timely delivery of any pending customer orders. Customers are well informed of the progress of their papers to ensure they keep track of what the writer is providing before the final draft is sent for grading.

5. Affordable Prices: Our prices are fairly structured to fit in all groups. Any customer willing to place their assignments with us can do so at very affordable prices. In addition, our customers enjoy regular discounts and bonuses.

6. 24/7 Customer Support: At Topnotch Essay, we have put in place a team of experts who answer to all customer inquiries promptly. The best part is the ever-availability of the team. Customers can make inquiries anytime.