Construction Management & scheduling FINAL PROJECT
Final Project
Total points: 300
Purpose and Scope:
You have been asked to create a comprehensive schedule report to present to the UT System for
an Office Building to be built on a university campus in Austin, Texas. The schedule will be
used in the presentation for a negotiated CM AT RISK contract. The following is the scope of
work as described by the owners.
The office building is to be built in an area that is pretty crowded on the campus along the MLK
Jr. Blvd. The project will start on October 15th, 2021, and finish on December 20th, 2024. It will
be a 4-Story building with Glass and Metal Curtain Wall / R/Conc. Frame. Further structural and
finishing details are provided in the attached cost estimate.
Figure 1. Selected spot for the building
Scheduling details according to the UT systems standard CM-at-risk contract:
1) Construction Manager shall cooperate with the Project Architect and endeavor to further the
interests of the Owner and the Project. Construction Manager shall furnish Pre-Construction
Phase Services and Construction Phase Services and complete the Project in an expeditious
and economical manner consistent with the interests of the Owner and in accordance with the
Project Schedule.
2) Proposal and all supporting documents shall identify and describe all items, assumptions,
costs, contingencies, schedules, and other matters necessary and relevant for proper
execution and completion of the Work.
3) The Construction Managers Pre-construction Phase Services team shall attend Project Team
meetings with the Owner, the Owners representatives, and the Project Architect at regularly
scheduled intervals throughout the Pre-Construction Phase.
4) Develop a critical path method schedule (CPM Schedule) for Project Team review and the
Owner’s approval, that coordinates and integrates activities on the Project, including the
Construction Manager’s services, the Project Architects design services, the work of other
consultants and suppliers, and the Owner’s activities with the anticipated construction
schedules for other contractors. The CPM Schedule must identify all major milestones
through Project Final Completion. The CPM Schedule shall be created and maintained
following the Owners Specifications using the Owner specified format and software.
5) The Construction Manager shall update the CPM Schedule throughout the Pre-Construction
and Construction Phases as described in the Owners Specifications. 6) At the Owners request, attend public meetings and hearings concerning the development and
schedule of the Project.
Deliverables:
A detailed estimate for the project has been provided to you. You can use the given estimate
activities in your schedule and SHOULD ADD activities for General Conditions,
Mobilization, and final clean up/occupancy. As the project manager, you need to schedule the
project in a way that will provide for the highest quality and in the shortest amount of time with a
safe work environment. Use MS Project to prepare the schedule. Plan for a 5-day work week
with normal holidays off. Think out the activities and relationships carefully and make this the
best-planned schedule you can for this project. Please consider the scheduling related details
mentioned above for a comprehensive schedule document.
There are two parts of the final project:
A. Project reports
1. It is company policy to have a complete as-planned schedule of the project shown in both
an organized, highly communicative bar chart and a pure logic diagram. The bar chart
will be used in a presentation with the owner and so it needs to be impressive and must
show the project by wings and by floor levels. The owner is very familiar with CPM and
has required the bar chart to show the activities in their early position and to show float.
2. A bar chart for the typical owner of milestone activities only. Milestone activities, in this
case, are construction activities the owner can be particularly interested in, probably some
of which are critical and some not critical.
3. A Network Logic Diagram of the total project. View the report and then add some
symbols or a logo to the footing of the report.
4. Your boss also wants to see the weekly cash flow requirements on the project as a
histogram and an early start S-Curve showing total cumulative costs.
B. Project Analysis
After completing the project reports, please answer the following questions:
What specific suggestions you can make in order to complete the project on the originally
scheduled completion date?
Please mention the months when you need the most credit in your hands and why it is so.
This is necessary to plan for having a sufficient amount of money available in those
months.
CE 5387: TERM PROJECT Fall 2020
Team Number:
Team Members:
Grading Criteria:
MAX PTS Comments
1 Submitted on Time (Due date: Friday, October 9, 2020 midnight)
N/A
2 Report looks professional- title page, table of contents, overall organization. 15
3 Project description and assumptions are included 20
4 Project reports (4 in total as described in the project report statement)
120
5 Project analysis questions 30
6 Conclusions(State the companys commitment to strong baseline schedule and project completion)
10
7 Appendixes: Meeting Minutes, RFI’s, etc. 5
8 Peer Evaluations 100
TOTAL 300