This document will focus on the areas excessive motion, cycle times, internal supply chain challenges. use value stream maps to document and analyzing process. You can do this document in auto cad or solid works.
Required No. Of Sets / Year 100,000 Sets / Year
No. Of Parts in a Set 8 parts
Required Total Number of Parts 800,000 Parts / Year
Working Days / Year 252 Working Days / Year
No. Of Sets / Day 397 Sets / Day
Total No. Of Parts / Day 3176 Parts / Day
Total No. Of Each Part / Day 397 Each Part / Day
Minutes of Work / Shift 420 Minutes of Work / Shift
No. Of Parts / Machine / Shift 33 Parts / Machine / Shift
No. Of Shifts / Day 3 Shifts / Day
No. Of Parts / Day / Machine 99 Parts / Day / Machine
No. Of Machines Deployed / Type of Part 4 Machine are Deployed / Type of Part.
Total No. Of Machine Required 32 Machines